Pittsboro Wastewater Treatment Plant, November 2026 Update
November 25, 2026
Every pump station gets built from the bottom up, and at the Pittsboro Wastewater Treatment Plant, the bottom is a long way down. Carolina Civilworks is building a new pump station there for TriRiver Water, and now that the excavation is finished, the concrete work has started.
Central Concrete tied the rebar for the wet well section of the base slab and set the forms. Then came the wet well pour: around 500 cubic yards of concrete, sent down into the hole with a big boom pump. That's pretty standard on a job like this, and the pour took about four hours.
After the wet well comes the dry well, with over 300 more yards to pour. From there it's a few more months of rebar, forms and concrete. This structure starts well below grade, but by the time we're built out it'll be above ground.
Next up, you'll see White Electrical get started on their underground work to support the new generator and electrical & controls building while the concrete work continues. Once the concrete is done, we'll test the structure, backfill it, and move on to piping, electrical and setting manholes.