North Village Regional Pump Station & Utilities
July 1, 2026
A look at progress on North Village Regional Pump Station & Utilities, where our team is building the regional pump station, sewer outfall, and associated force main that will serve a future master-planned community.
One of the first milestones on site was setting the wet well for the pump station. From there, crews moved into laying the gravity sewer through the outfall, with the force main to follow to wrap up the line work portion of the project. Next up, a second crew mobilizes to take on the pump station's mechanical scope (pumps, piping, and valves), putting two crews on site for the stretch ahead.
By the numbers:
Over 4,500 LF of 12" force main
Almost 5,000 LF of 12” gravity sewer
We're self-performing the majority of the work, with the exception of clearing, blasting, electrical, precast coatings, and fencing.
Big thanks to our partners:
@AllErectionCrane
@sunstateequipment9573
@Dunrite Services
@East Coast Drilling & Blasting
@Southeastern Erosion Control
@NGE Services
@Wilson & Cofield Electric