Pump Station 12 Force Main Replacement
Owner / GC
Cape Fear Public Utility Authority
value
$1,520,000.00
Completed date
June 2019
In May 2018, CCI was awarded this project to replace approx. 5,000 LF of existing force main with a new 16” PVC line. The majority of the alignment was through downtown streets occupied by businesses and single family homes. Traffic control, communication and phasing of the work were key to reducing impacts to CFPUA’s customers. Also included on this job were a horizontal directional drill and various storm drain improvements throughout the project corridor.